NEW QUESTION # 22
For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question.

  • A. The deletion flag must NOT be set for the bill of material (BOM) or the routing.
  • B. The consistency check must be performed.
  • C. The assigned routing and bill of material (BOM) must have the same validity period.
  • D. The lot size range must be within the lot size range of the assigned routing.
  • E. The assigned routing and bill of material (BOM) must be valid in the entire validity period.

Answer: B,D,E


NEW QUESTION # 23
You use the Finite Scheduling - with Reverse planning strategy and want to allow scheduling in the past.
How can you parameterize this in the strategy profile?

  • A. Specify a negative opening period
  • B. Specify a negative planning horizon
  • C. Specify a negative PP/DS horizon
  • D. Specify a negative offset time

Answer: D


NEW QUESTION # 24
Which of the following would you recommend as SAP's strategic Sales and Operations planning tool?

  • A. Advanced Planning
  • B. Integrated Business Planning
  • C. Flexible Planning
  • D. Standard Sales and Operations Planning

Answer: B


NEW QUESTION # 25
What can you use standard heuristics in Advanced Planning (PP/DS) for?

  • A. To solve planning problems for defined objects
  • B. To optimize costs and times in production plans
  • C. To set default values in production master data
  • D. To automate material movements in material staging

Answer: A


NEW QUESTION # 26
Which objects can you change with a change number?
Note: There are 2 correct answers to this question.

  • A. Production order
  • B. Routings
  • C. Work center
  • D. Bill of material

Answer: B,D


NEW QUESTION # 27
When can you maintain the batch characteristic values in SAP S/4HANA?
Note: There are 2 correct answers to this question.

  • A. When you post the goods receipt
  • B. When you record inspection results
  • C. When you execute batch determination
  • D. When you release the batch

Answer: A,B


NEW QUESTION # 28
What are some advantages of using Kanban for material supply? Note: There are 2 correct answers to this question.

  • A. Material stock is built up for a long period of time in production.
  • B. Replenishment is always triggered on a regular basis.
  • C. Replenishment is only triggered when components are required.
  • D. Material is only kept available in small quantities in production.

Answer: C,D


NEW QUESTION # 29
How would you define a pegging structure for an order in the context of Advanced Planning?

  • A. An evaluation that is ordered according to the low-level codes of all related products and represents the coverage of issue elements with receipt elements and stock
  • B. An evaluation to identify material or capacity shortages in the bill-of-material structure after the production planning run
  • C. An evaluation to identify overstock situations based on the assignment of receipt and issue elements after the production planning run
  • D. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between receipt and issue elements

Answer: D


NEW QUESTION # 30
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

  • A. Requirements type
  • B. Planning strategy
  • C. Requirements profile
  • D. Order type

Answer: A,B


NEW QUESTION # 31
Why would you use phantom assemblies?
Note: There are 2 correct answers to this question.

  • A. To enable simple structuring of BOMs
  • B. To make the assignment of components easier
  • C. To make the procurement easier
  • D. To reduce the number of material masters

Answer: A,B


NEW QUESTION # 32
Which time elements are relevant for lead time scheduling of a production order?
Note: There are 2 correct answers to this question.

  • A. Float after production
  • B. Setup time
  • C. Opening period
  • D. Total replenishment lead time

Answer: A,B


NEW QUESTION # 33
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

  • A. When alternative resources are used within one operation
  • B. When several operations are maintained for one product
  • C. When several production versions are maintained for one product
  • D. When multiple planned orders are scheduled in parallel on one resource

Answer: A


NEW QUESTION # 34
How can you limit the validity of a bill of material (BOM)?
Note: There are 2 correct answers to this question.

  • A. By material type
  • B. By plant
  • C. By change number
  • D. By material status

Answer: A,B


NEW QUESTION # 35
Which of the following processes lead to an indicator in the planning file?
Note: There are 2 correct answers to this question.

  • A. Changing an operation time
  • B. Changing a dependent requirement
  • C. Changing a storage bin
  • D. Changing a delivery address

Answer: A,B


NEW QUESTION # 36
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.

  • A. Scheduling agreement schedule line
  • B. Purchase order
  • C. Production order
  • D. Planned order

Answer: A,D


NEW QUESTION # 37
Advanced Planning uses data from SAP S/4HANA Cloud Private Edition. In which master data objects can you set the Advanced Planning flag?
Note: There are 2 correct answers to this question.

  • A. Production version
  • B. Material
  • C. Plant
  • D. Work center

Answer: B,D


NEW QUESTION # 38
How can you set up a material as a phantom assembly?
Note: There are 2 correct answers to this question.

  • A. Select a special procurement type inside the material BOM (bill of material)
  • B. Select a special explosion type inside the material master
  • C. Select a special procurement type inside the material master
  • D. Select a special explosion type inside the material BOM (bill of material)

Answer: A,C


NEW QUESTION # 39
Which options do you have to post goods receipt for a process order?
Note: There are 2 correct answers to this question.

  • A. You post the entire manufactured quantity to multiple batches if the product quality changes during production.
  • B. You post the entire manufactured quantity to one batch if the product quality remains consistent during production.
  • C. You post the entire manufactured quantity to one batch if the product quality changes during production.
  • D. You post the entire manufactured quantity to multiple batches if the product quality remains consistent during production.

Answer: A,B


NEW QUESTION # 40
What is the purpose of the pull list in material staging?

  • A. To control the flow of material from the supplier to the production storage location
  • B. To control the flow of material from the production storage location to the central storage location
  • C. To control the flow of material from the central storage location to the production storage location
  • D. To control the flow of material from the supplier to the central storage location

Answer: C


NEW QUESTION # 41
Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision?
Note: There are 3 correct answers to this question.

  • A. Net requirements calculation is carried out for every sales order individually.
  • B. Planned orders are created in MRP with reference to sales orders.
  • C. Production and procurement costs are managed on the sales order item level.
  • D. Sales orders have to be ATP-confirmed (available-to-promise) to be saved.
  • E. Storage location MRP areas are required to manage sales-order-specific stock.

Answer: A,B,C


NEW QUESTION # 42
......

All C_P2W22_2504 Dumps and Training Courses: https://examsboost.actual4dumps.com/C_P2W22_2504-study-material.html